Delayed L1 conversions in Maharashtra
Four L1 projects in Maharashtra (total ~₹7,700 crore) face uncertainty due to land acquisition issues; management is engaging with the government but outcome is unclear.
Afcons Infrastructure · risk themes across the available quarters.
Bear-case history
Four L1 projects in Maharashtra (total ~₹7,700 crore) face uncertainty due to land acquisition issues; management is engaging with the government but outcome is unclear.
₹450 crore receivables and ₹600-650 crore unexecuted work stalled due to client payment delays; work has been stopped and demobilized.
Second consignment of TBMs for high-speed rail project is stuck at port for two months; delay could push execution start to Q1 FY27.
Net debt rose to ₹2,714 crore due to delayed certifications and payment stretch; interest-bearing advances doubled to 40% of total advances.
Large L1 orders (₹11,300 crore) including Croatia and Maharashtra projects face delays; Maharashtra projects may be rebid, risking order inflow targets.
Second consignment of TBM from China is awaiting clearance, impacting project timelines and capex plans.
A ₹191 crore bank guarantee was encashed by the client; recovery depends on ICC arbitration, with no immediate impact on P&L but debt increased.
Management noted rising competitive intensity in metros with aggressive bidding, which could pressure margins on new orders.