Capex roadmap of $5 billion by 2030
Management outlined a capital expenditure roadmap of approximately $5 billion to be achieved by 2030, financed through internal accruals and disciplined debt use.
Aegis Vopak Terminals · forward-looking guidance across the available source record.
Guidance tracker
Management outlined a capital expenditure roadmap of approximately $5 billion to be achieved by 2030, financed through internal accruals and disciplined debt use.
First phase of new liquid capacity at JNPT (part of ₹1,675 crore project) scheduled to come online in Q1 of FY27.
The Kandla-Gorakhpur LPG pipeline is expected to be connected by June 2026, enabling significant throughput increase.
Management committed to maintaining a debt gearing ratio of 0.6 times and overall leverage not exceeding 3.5 times EBITDA.
Management expects throughput to grow 30-40% year-on-year in FY27, consistent with historical trends.
Aggregate capex will reach approximately $1.2 billion by end of FY27, with FY28 capex expected around ₹5,000 crore.
First phase of 318,100 cbm liquid expansion at JNPT expected to be operational in Q1 FY27, contributing from Q2.
India's first independent ammonia terminal at Pipavav (36,000 MT) expected to be commissioned in H1 FY27.