Pipeline commissioning delays

The Kandla-Gorakhpur pipeline timeline slipped from March to June 2026 due to land compensation challenges.

medium

LPG import growth slowdown

Year-to-date LPG import growth slowed to ~8%, with month-on-month volatility due to inventory management by oil companies.

low

Execution risk on large capex

The $1.2 billion capex plan by FY27 and $5 billion by 2030 require timely execution and funding, with potential cost overruns.

medium