Capacity expansion to 30 GW by FY30

Targeting 30 GW capacity by 2029-30 from current 15 GW, including 1,600 MW Mahan Phase 2 (by June 2027) and 4,800 MW brownfield expansions.

expansion

80% PPA tie-up for new capacity

New projects will have 80% capacity tied to long-term PPAs (25-year duration) and 20% kept for merchant sales.

revenue

Inorganic acquisitions of Lanco Amarkantak and Coastal Energen

Awaiting NCLT approval for resolution plans; Lanco adds 600 MW (tied up) and 1,320 MW under construction; Coastal adds 1,200 MW (600 MW tied up).

expansion

Capacity expansion target of 12,520 MW by 2030

Management reiterated target to add 12,520 MW by 2030, with 4,800 MW under execution. Boiler, turbine, and generator supplies locked for entire 11.2 GW new capacity.

expansion

Stable EBITDA margins expected in FY26

CFO stated that until capacity expansion takes place, similar EBITDA margins as last year can be expected.

margins

Deroli mine production to start by Sep-Oct 2025

CEO confirmed production from Deroli mine is on track to start by September or October 2025.

other

No SGD requirement for new plants, reducing project cost

Following government notification, SGD will be dropped from new plants except Mahan and Raipur, lowering capital cost.

capex

Capacity target of 30.67 GW by 2030

Plans to double capacity from ~15 GW to 30.67 GW through organic expansion (Mahan Phase II, Raipur, Raigarh, Mirzapur) and acquisitions (Lanco, Coastal).

growth

80% PPA tie-up for new capacity

Management aims to secure long-term PPAs for 80% of new capacity, keeping 20% for merchant sales to balance risk and reward.

revenue

Mahan Phase II completion by June 2027

The 1,600 MW ultra-supercritical expansion at Mahan is on track for commissioning by June 2027.

expansion

Merchant tariff expected to average ~INR 6/unit in H2 FY26

Management expects merchant realization to recover to around INR 6 per unit in the second half, from INR 5.37 in Q2.

revenue

Godda plant to connect to Indian grid by December 2025

The Godda power plant is expected to be connected to the Indian grid by December 2025, allowing sales under certain conditions.

expansion

First 12 GW of expansion on track; 3 GW commissioning next year

The first 12 GW of the 23.5 GW expansion is on schedule, with ~3 GW expected to commission in FY27, followed by 2.4 GW, 3.2 GW, and 7.2 GW in subsequent years.

growth

Total CapEx for 23.5 GW expansion ~INR 2 lakh crore

The estimated capital expenditure for the entire 23.5 GW capacity expansion is approximately INR 2 lakh crore.

capex

Raipur expansion to commission within 4 years

The 1,600 MW Raipur expansion project (PPA with MSEDCL for 1,496 MW) is planned to commission within 4 years, though PPA allows 5 years.

expansion

Korba (Lanco) expansion to commission in ~30 months

The 1,320 MW Korba expansion project is expected to commission in about 30 months from the call date, with estimated CapEx of INR 10,000 crore.

expansion

Rohne coal mine to supply 5 MTPA after 2 years

The Rohne mine, acquired from Adani Enterprises, will supply 5 million tons of coal per annum after two years for the Mahan plant's untied capacity.

growth

Target 30 GW operating capacity by 2030

Management reiterated the target to achieve more than 30 GW of operating capacity by 2030, with BTG orders placed for 11.2 GW.

growth

Capacity expansion of 23.7 GW by FY32

Planned addition of 23.7 GW thermal capacity, with 2.9 GW commissioning next fiscal, 2.4 GW in FY28, 2.4 GW in FY29, 8 GW in FY30, 5.6 GW in FY31, and 2.4 GW in FY32.

expansion

Reduce open capacity to 3-4% over 6-7 years

Management targets reducing merchant exposure from current 10% to 3-4% over the medium term by signing more long-term PPAs.

growth

Korba Phase 2 commissioning by end of next fiscal

First unit of Korba Phase 2 expected around mid-next year, second unit by end of next fiscal.

expansion

Capex of INR 13,000 crore for FY26

The company plans to spend INR 13,000 crore on capital expenditure in FY2026 for its expansion projects.

capex

Mahan Phase II commissioning by March 2027

The 1,600 MW Mahan expansion project is expected to be commissioned around March or April 2027.

growth

Capacity expansion to 30,670 MW by 2030

Adani Power targets to increase its total capacity to 30,670 MW by 2030 through brownfield expansions.

growth

Funding capex through internal accruals

Management stated that the entire capex plan will be funded from internal accruals without additional debt.

other

Korba Phase 2 commissioning in Q2 FY27

The 1.32 GW Korba Phase 2 project is expected to commission between June and September 2026.

expansion

Mahan commissioning by Q4 FY27/Q1 FY28

First unit of Mahan (1.6 GW) likely by end of FY27, second unit six months later.

expansion

Capex of ₹25,000 cr in FY27 and ₹33,000 cr in FY28

Capital expenditure for capacity expansion estimated at ₹25,000 crore in FY27 and ₹33,000 crore in FY28.

capex

EBITDA target of ₹50,000 crore by FY30-31

Management expects EBITDA to reach ₹50,000 crore by 2030-31, driven by capacity expansion and new PPAs.

growth