ACMESOLARHOLDINGS / Q4-FY26 / claim-ledger

Audit the questions that mattered.

Acme Solar Holdings · Analyst questions, management answers, and the quality of the response where the ledger is available.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

PositiveQ4-FY26 · 2026-05-15Back to quarter ↗

Questions audited

12

Answered directly

88%

Numeric claims

2

Consistency

contradicted

Question ledger

What was answered, and how?

Pune · HSBC

partial

Battery capex in previous year and current quarter for 2.3 GW commissioned

last quarter we did around in this quarter so far current quarter currently last quarter was around 1,000,000 to 1200 crores

Pune · HSBC

partial

Run rate from existing capacity with and without battery

for the last full year including other income has been around 2200 odd cr. ... 2.3 GW is currently operational ... delivering give or take uh average net relation of 2.2 cr per day which is effectively more than 60 cr per month

Pune · HSBC

direct

PLF of new solar plants commissioned in FY25 for FY26

our seeker plant basically got commissioned ... doing close to around 29 to 30% a year for the overall year. ... for the new plant it is because we have a higher DC installed there so it has a higher CUF yeah for the full it's been close to 26% for the entire portfolio

Pune · HSBC

direct

Economics change for SEISTS hybrid trans 6 scheme with battery inclusion

it basically uh keeps the return in uh in uh high teens only. So it does not impact really uh the returns

Karthik Sharma · Arandati

direct

Curtailment impact in Q4 and full year, future project allocation

for the whole year we have only five to six crores of impact on the curtailment which is the real curtailment ... all of our projects are in the uh CTU ... we have consciously built a portfolio with ... all the central counterparties on CTU

Karthik Sharma · Arandati

direct

Sustainability of sharp improvement in receivables and DSO

our portfolio as it gets more operational it is shifting towards 100% central ... they pay in 10 days ... that is why we are getting a 15 days kind of a receivable cycle today. So which is more or less not because of oneoff it is it is the norm.

Anikit Mal · SBI mutual fund

direct

Reason for large increase in non-current assets and impact on cash flow

these are mainly include the capital credits actually. ... capital advances of roughly 323 crores ... given to for the procurement of material

Anikit Mal · SBI mutual fund

partial

Reason for 1% decline in PL on a YoY basis this quarter

could be a function of of course the uh lower radiation or and cartilagement. These these two could be the only two factors which would have impacted on a yi basis.

Anikit Mal · SBI mutual fund

direct

Merchant 654 MWh in under construction portfolio - purpose

it is uh merchant as of now uh it is uh slated to go to a PPA uh which we are supposed to sign very shortly. ... it gives us some flexibility ... we also wanted to uh get it financed on a merchant basis

Anikit Mal · SBI mutual fund

direct

Commissioning timeline for SGB, FDR, and NTPC hybrid projects in FY27

by March 27 all this will be commissioned. ... we are targeting ... around 2500 megawatt of ready connectivity for selling battery power during night ... battery commissionings are going to happen early

Isan · Antic Stock Broking

direct

Impact of CERC's new mechanism for LOA connectivity on Acme's inventory

we have around 62 gawatt of signed PPA which we are constructing ... our LOAs are more or less converted into PPA ... we don't foresee that our LOAs will uh we will have to surrender

Duven Sha · HDFC Securities

direct

Merchant vs FDR split of 10 GWh battery commissioning and EBITDA margins

around 8 and 1/2 gawatt hour out of this 10 gawatt hour would be on uh merchant and 1 and a half gawatt hour would be in the fd format. ... assuming a tariff arbitrage of 6 rupees ... give or take the margin will be around 75 to 80%.