Transmission delays from CTU
CTU substation delays of up to 6 months could push project commissioning timelines, though management defers module procurement to mitigate.
medium · analyst_questionAcme Solar delivered a strong Q4 FY26 with total revenue of INR 705 crore, up 31% YoY, driven by capacity additions and higher CUF.
✓ Verified against BSE filing
Concise cards keep the risk register scannable while preserving evidence-level context in the underlying quarter data.
CTU substation delays of up to 6 months could push project commissioning timelines, though management defers module procurement to mitigate.
medium · analyst_questionThe high arbitrage between peak and off-peak power prices may narrow as more BESS capacity is added, impacting merchant returns.
medium · analyst_questionUnsigned PPAs for ~850 MW of older LOAs could face conversion delays if discoms are slow, though management expects resolution.