Shakti Pumps Management Guidance Tracker
8 forward-looking guidance items tracked across 2 quarters.
Revenue
Management expects Q4 FY26 to be the highest revenue quarter in the company's history, driven by resumed execution in Maharashtra and new orders.
Q3 FY26Full-year FY26 revenue guidance close to targetActiveManagement aims to achieve close to the earlier revenue guidance for FY26, though some spillover into Q1 FY27 is possible.
Capex
The 500 MW solar module plant is expected to be commissioned in Q1 FY27, supporting backward integration and margin improvement.
Q3 FY26Solar cell + module capacity of 2.2 GW by April 2027TrackedThe larger 2.2 GW solar cell and module plant is expected to be operational by April 2027, with total capex of ~₹1,200 crore.
Q4 FY260.5 GW solar module plant commissioning by Q1 FY27 endActiveThe 0.5 GW module plant is progressing well and expected to be operational by end of Q1 FY27, which should aid margin improvement.
Q4 FY26Solar cell capacity (2.2 GW) by March 2028TrackedThe 2.2 GW solar cell capacity is targeted for commissioning by March 2028.
Growth
Management expects KUSUM 2.0 scheme to be announced in Q1 FY27, with orders flowing from Q2 onwards, based on recent PM announcement.
Q4 FY26Year-on-year growth to continueActiveManagement stated they will maintain year-on-year growth and deliver better numbers, but did not provide a specific revenue target.