Transformer and Reactor Supply Chain Bottleneck

Domestic manufacturing capacity at 2.28 lakh MVA against projected demand of 4.21 lakh MVA in FY27. Government is considering relaxation for Chinese companies to set up manufacturing in India, which if approved would boost supply.

high

Right-of-Way Issues Persist Despite Improved Guidelines

Though government guidelines (June 2024, March 2025, December 2025) have improved execution, ROW remains a pain point requiring continued engagement with state governments and chief ministers.

medium

Forest and Wildlife Clearances Continue to Delay Projects

Management acknowledged this remains a challenge; discussions ongoing with government of India for resolution, though no timeline provided.

medium

Market Share Concentration in Competitive Bidding

While maintaining 50-60% market share in TBCB projects, competition is intensifying with competitor claiming ₹75,000 crore works in hand including HVDC projects. HVDC projects have only 3 global manufacturers (Hitachi, ABB, Siemens) creating execution dependencies.