FY26 Capitalization Target: Rs 20,000 crore
Management reaffirmed Rs 20,000 crore project commissioning target for FY26 despite H1 achieving only Rs 4,587 crore. Projects delayed due to RoW approvals expected in Q3-Q4.
Powergridofindia · forward-looking guidance across the available source record.
Guidance tracker
Management reaffirmed Rs 20,000 crore project commissioning target for FY26 despite H1 achieving only Rs 4,587 crore. Projects delayed due to RoW approvals expected in Q3-Q4.
Capex for FY27 guided at Rs 28,000 crore with TBCB projects worth Rs 19,062 crore and RTM Rs 3,554 crore.
FY28 capex guidance of Rs 35,000 crore reflecting continued scale-up of execution capacity.
Given ~2-year lag between capex and capitalization, FY27 capitalization expected at Rs 25,000-26,000 crore based on Rs 26,000 crore FY25 capex.
9-month capex of ₹29,200 crore already exceeds original ₹28,000 crore target; management confident of surpassing ₹32,000 crore by fiscal year-end.
Committed to government of India for FY27 capex of ₹37,000 crore, representing 16% increase over FY26 revised target.
Major HVDC projects (Bikaner-South, Bikaner-Bhuj) driving significant capex escalation to ₹45,000 crore in FY28 as equipment supply and execution accelerate.
Already commissioned ₹18,700 crore of projects by January 31, 2026; target exceeds original ₹20,000 crore guidance with major elements (Bhadla3-Sikar2, Navsari-Fatehgarh, Kundul3-Maheshwaram) slated for Q4 completion.