HAM Project Execution Ramp-Up Risk

Four HAM projects worth Rs 5,000 crore have been delayed by 2 years due to land acquisition issues. Management needs to achieve ~Rs 1,000 crore revenue from these projects in FY26 to meet guidance—analyst questioned feasibility given typical mobilization lead time.

high

SITCO Project Stay Continuation

Rs 240 crore irrigation project remains halted due to judicial matter under sub judice. Physical execution suspended; management declined to share further details citing sensitivity.

medium

Toll Road Asset Depletion

Kuruwasi highway project concession ended January 2025, eliminating toll revenue stream from Q1 FY26 onward. No replacement toll assets identified in near-term pipeline.

medium

Order Award Timing Uncertainty

Analyst directly challenged management's optimism on NHA awarding Rs 3 lakh crore of projects, noting 18-24 months of order drought. Management attributed delays to cyclical factors and maintained positive outlook citing government infrastructure thrust.

medium