Risk intelligence

Material risks this quarter

Renewable Transmission Connectivity Shortfall

Only 57% firm connectivity secured for FY27 renewable capacity (4,237 MW), with 38% dependent on T-GNA. Remaining 9% for FY28 also not tied up, risking curtailment and delayed commissioning.

high

Thermal Backing Down During Solar Hours

Thermal units face technical minimum constraints at 55% PLF during daytime solar peaks. Grid curtailment of 314 MUs and 135 MUs brass loss occurred in FY26, with ~₹90 crore financial impact.

medium

NGEL Pipeline Reduction

NGEL's total project pipeline declined from 32 GW to 30 GW as management 'normalized' numbers based on JV progress assessment. Analyst raised concern about project removals without clear explanation.

medium

Competitive Bidding Volume Uncertainty

FY26 saw lower project wins through tariff competitive bidding as NGL stayed away due to unattractive terms. Management did not commit to returning to 2-3 GW annual win rate achieved in FY24-25.

medium