8 GW Renewable Capacity by FY28, 10 GW by FY30
Pipeline built through JVs with Rajasthan (2 GW), Assam (1 GW), Maharashtra/Mahapri (~5 GW), and Odisha (~2 GW). 3 GW already in advanced implementation stages.
NLC India · forward-looking guidance across the available source record.
Guidance tracker
Pipeline built through JVs with Rajasthan (2 GW), Assam (1 GW), Maharashtra/Mahapri (~5 GW), and Odisha (~2 GW). 3 GW already in advanced implementation stages.
Cabinet approval and tax exemptions received. All activities in fast progress; management expects to list in September 2026.
Gatamur full station (3×660 MW) to be fully operational this financial year. Capacity additions to ramp up sharply from FY27 onward.
Pachwara South mine commenced operations December 2025; will fully supply Gatamur's ~6 MMT annual requirement. Talabira production at 2 MMT in FY27, bridging 4 MMT via Coal India linkage.