Teesta-V restoration delay
October 2023 flash flood caused complete shutdown; August 2024 landslide further delayed restoration. If January 2026 deadline is missed, INR 300+ crore annual PBT from Teesta-V remains at risk.
NHPC · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
October 2023 flash flood caused complete shutdown; August 2024 landslide further delayed restoration. If January 2026 deadline is missed, INR 300+ crore annual PBT from Teesta-V remains at risk.
Combined PBT loss from Teesta-V, TLDP-III, and TLDP-IV is INR 400 crore versus normal INR 500 crore profit, directly impacting profitability. Management acknowledged this as the primary driver of PAT decline.
PF-based incentive declined INR 89 crore YoY to INR 227 crore, while secondary energy increased only INR 21 crore. Total incentive income dropped INR 74 crore, reflecting operational underperformance.
Parbati-II (~INR 2,000 crore annual revenue) and Subansiri (~INR 4,500 crore) await CERC tariff orders. Management will recognize only 90% provisionally, creating earnings visibility risk.