Subansiri Lower Phase 1 Commissioning

Three units of the 2,000 MW project expected to commission by March 2025, with remaining five units in phased manner through May 2026.

expansion

Parvati-II Project Commissioning

98% progress achieved with all major works completed except 159m overt lining and 3,630m invert lining of HRT; project targeted for February 2025.

expansion

Teesta-V Restoration

The power station suffered second incident in August 2024 (landslide at tail race tunnel); restoration expected to be completed by December 2025.

expansion

Regulated Equity Growth

Projected to reach INR 16,500Cr by FY25 end, INR 17,000Cr by FY26, INR 25,365Cr by FY27, and INR 28,590Cr by FY28.

revenue

FY26 Consolidated CapEx: INR 13,300 crore

Nine-month consolidated CapEx already at INR 8,844 crore vs INR 7,405 crore in prior year period, tracking towards full-year target.

capex

FY27 CapEx: INR 15,000 crore

Significant increase planned for next fiscal year to support the ambitious project pipeline including multiple hydro projects and solar expansion.

capex

FY27 Capacity Addition: 2,744 MW from Hydro

Based on current project timelines, NHPC expects to add approximately 2,744 MW of hydroelectric capacity in FY27, primarily from Subansiri Lower (remaining 6 units), Pakal Dul, and Kiru projects.

expansion

Annual CapEx Run-rate: INR 12,000-13,000 crore post-FY27

Management expects sustained high CapEx phase as ~10,000 MW of new hydro projects (Uri-I Stage-II, Dulhasti Stage-II, Sawalkot, Subansiri Upper, Etalin, Kamala) enter construction.

capex

Subansiri Lower commissioning timeline

3 units expected by June 2025, remaining 5 units by May 2026. Project at 96% physical progress with incremental annual revenue of INR 4,500 crore when fully operational.

expansion

Parbati-II revenue recognition

With 800 MW capitalized (INR 12,000+ crore), the project will generate ~INR 2,000 crore annual revenue at INR 7.5/unit tariff. CERC tariff petition to be filed; 90% revenue recognized provisionally till order.

revenue

Teesta-V restoration

Restoration works progressing; affected by August 2024 landslide. Expected completion by January 2026. Teesta Basin projects normally contribute ~INR 500 crore PBT.

expansion

Regulated equity expansion

Consolidated regulated equity of INR 15,000 crore; expected to reach INR 18,000 crore after Parbati-II capitalization (30% of INR 12,000 crore capital cost).