Material risks this quarter

JDA contribution above target compressing margins

JDA contributed ~50% of pre-sales this quarter versus the 40% target. While embedded EBITDA margin of 32% was maintained, owned land margins (37-38%) are 10 percentage points higher than JDA (27%), creating margin headwinds if mix remains elevated.

medium

Data center strategy remains early-stage with key details unconfirmed

Management acknowledged the business plan is still underway and will provide details in the next quarterly update. Power shell capex (~$300-350 million for 250 MW), partnership structures, speculative vs. BTS approach, and timeline to 250 MW capacity remain undefined. Risk of overpromising on unconfirmed opportunity.

medium

Environmental clearance delays bunched H2 launches, creating execution risk

Mumbai environmental clearances were stalled for ~12 months (Aug 2024 - Aug 2025), pushing launches to H2. Management targets returning to more spread-out launch cadence next fiscal, but execution of multiple H2 launches simultaneously carries risk.

medium

Pune/Bangalore scaling assumptions unverified at larger base

Pune grew from ₹200 crore (FY21) to ~₹2,500 crore (FY25). Management targets becoming #1 in Pune within 2 years and ~30% of pre-sales from non-Mumbai markets. These ambitious targets for nascent operations lack detailed milestones for external verification.