Risks carried through the record.

Rajasthan government tender paralysis

Tender finalization has stalled for 6-8 months in Rajasthan with repeated cancellations and re-tenders. RVPNL accounts for 72% of the order book, creating severe concentration risk if delays persist through FY27.

high

Geopolitical supply chain disruption risk

ERS shipments from the UAE faced 6+ week delays impacting ₹50-60 crore of revenue recognition in Q4. While 50% has been executed, the remaining faces continued uncertainty if shipping disruptions extend.

medium

Working capital deployment strain

With only ₹19 crore cash on books and ₹45 crore of ₹50 crore fund-based limits utilized, the company's ability to bid aggressively on ₹300 crore pipeline and fund future growth is constrained until retention releases.

medium

Margin erosion from fixed-price exposure

Approximately ₹50 crore of fixed-price contracts exist within the order book. Raw material prices have risen 40-50% suddenly, and while 80% of price variation passes through to customers, 20% impacts margins.

medium