Transmission Infrastructure Delays
Analyst (Punit/HSBC) raised concerns about potential transmission delays affecting the 2 GW FY27 target. Management responded that substations are largely operational but one substation with ~300 MW has some remaining work expected by December. They have contingency plans using battery storage on TGNA to run merchant while awaiting full GNA connectivity.