FY27 Capacity Addition: 2 GW
Company targets 2 GW of renewable capacity commissioning in FY27, with 760 MW already commissioned through July 10. Remaining ~300 MW in Q2 on STU projects, balance 1 GW on CTU with substations operational by December.
Juniper Green Energy · forward-looking guidance across the available source record.
Guidance tracker
Company targets 2 GW of renewable capacity commissioning in FY27, with 760 MW already commissioned through July 10. Remaining ~300 MW in Q2 on STU projects, balance 1 GW on CTU with substations operational by December.
Management guided run-rate EBITDA of approximately ₹2,700 crore for the 4 GW capacity that will be operational by March 2027, implying significant earnings ramp as new capacity gets commissioned and stabilizes.
By FY28, the company targets 6 GW of commissioned capacity with run-rate EBITDA of ₹4,500 crore, nearly doubling from FY27 levels as the project pipeline moves to operations.
Company targets 4.5 GWh of battery storage by June 2027 and 10 GWh by March 2028. 1.5 GWh of this will run as merchant capacity for 1-2 years before being absorbed into PPAs.