Material risks this quarter

Fujairah Geopolitical Risk

Three of 15 tanks damaged at Fujairah oil storage facility following infrastructure damage. Operations remain volatile with geopolitical tensions in Middle East. Management expects ~50% capacity to resume in June 2026 with balance ramping up in phases, but timeline remains uncertain given security situation.

high

Dharamtar Environmental Compliance

Environmental committee flagged dust spillover onto mangroves at Dharamtar Port. Management is providing wind screens to comply with conditions. Execution timeline maintained but ongoing regulatory scrutiny could impact future permitting.

medium

Insurance Claim Uncertainty

Although assets and loss of profit are covered by insurance, management took INR 68 crore provision as precaution given unprecedented nature of incident in the region. Admissibility of full claims remains uncertain.

medium

Morbi ICD Fuel Shortage Impact

Fuel shortages impacted certain customers at Morbi ICD during Q4, creating headwinds for that facility. Management did not quantify the impact or provide timeline for resolution.