Risk intelligence

Material risks this quarter

PPA signing pendency for 2.6 GW

Of the ~40 GW of awarded projects industry-wide pending PPA signing, JSW has 2.6 GW (including 900 MW solar) pending. Management declined to provide timeline for conversion.

medium

BESS cost and tariff opacity

Analyst pressed for BESS capital cost benchmarks (landed cost per MWh) and comparison with solar tariffs. Management declined to provide specific numbers, citing competitive sensitivity and project-specific variables.

medium

H2 execution ramp-up required

H1 capacity additions were limited compared to plans. Management acknowledged extended monsoon slowed execution in H1 and expects higher additions in H2 to meet FY26 targets.

medium

Renewable generation decline

Maitra wind portfolio EBITDA slightly declined YoY despite higher wind speeds due to old 850 kW machines limiting incremental benefit. Solar performance impacted by extended monsoon and lower radiation.

low