Expansion
The 150 KPD expansion at Bathinda and Swaksha's capacity increase to 350 KPD will bring total capacity to 900 KPD by Q4 FY26.
Q3 FY26Maize extraction unit commissioning in Q4 FY26ActiveThe maize oil extraction unit at Swaksha is on track to be commissioned by Q4 FY26, expected to improve margins modestly.
Q4 FY26250 KPD distillery expansion at Patabad in ~2 yearsTrackedPlanned additional 250 KPD distillery at Patabad, Haryana, expected to be commissioned in about two years, subject to policy environment.
Q4 FY26CBG plant at Patabad within 3 yearsTrackedA 20 TPD compressed biogas plant is planned at Patabad, expected to be operational within three years, after the distillery expansion.
Revenue
Management indicated they expect to achieve ₹3,000 crore revenue for FY26, implying ~40% growth, though dependent on ethanol allocations.
Q4 FY26New 150 KPD unit to contribute ~₹300 crore revenue at full utilizationTrackedManagement expects the new Barnala distillery to generate around ₹300 crore in revenue when operated at 100% capacity.