Aegis Vopak Terminals Management Guidance Tracker
8 forward-looking guidance items tracked across 2 quarters.
Capex
Management outlined a capital expenditure roadmap of approximately $5 billion to be achieved by 2030, financed through internal accruals and disciplined debt use.
Q4 FY26Capex of ~$1.2 billion by end of FY27, ~₹5,000 crore in FY28TrackedAggregate capex will reach approximately $1.2 billion by end of FY27, with FY28 capex expected around ₹5,000 crore.
Expansion
First phase of new liquid capacity at JNPT (part of ₹1,675 crore project) scheduled to come online in Q1 of FY27.
Q3 FY26Kandla-Gorakhpur LPG pipeline operational by June 2026TrackedThe Kandla-Gorakhpur LPG pipeline is expected to be connected by June 2026, enabling significant throughput increase.
Q4 FY26JNPT liquid expansion first phase operational in Q1 FY27ActiveFirst phase of 318,100 cbm liquid expansion at JNPT expected to be operational in Q1 FY27, contributing from Q2.
Q4 FY26Pipavav ammonia terminal commissioning in H1 FY27ActiveIndia's first independent ammonia terminal at Pipavav (36,000 MT) expected to be commissioned in H1 FY27.